TEXT:
Three photos on projects on 101 under construction. One is of the Dyerville bypass job. Two photos. The other is the 3.5 mile Patricks Pt to north end of causeway at Big Lagoon. This job is 52% complete and includes just the grading. The paving will be done next year (1958) along with construction of the bridge. The 58' roadbed on the causeway will be 20' above the bottom of the lagoon. The work began on January 14th, 1957. The new bridge will be 450 feet long.