You are here

Dedication of construction of tunnel through Oregon Mtn.

DT Data Page #: 
360
Newspaper: 
Humboldt Times
Newspaper Date: 
8/13/1961
Page #: 
1 & 5
Column: 
1
Item Type: 
Dedication
Place: 
Oregon Mtn. Hazel View Tunnel
TEXT: 
The work on construction a tunnel through Oregon Mtn is described. There were great challenges at the start. They are now 400ft into the mtn. The 14' X 14' feet bore will be enlarged to 43' feet wide to 20' feet tall. There is a photo taken inside the 14' X 14' foot tunnel.
Key Words: 
Tunnel, Construction, Oregon Mtn.