Rock delivering

DT Data Page #: 
470
Newspaper: 
Humboldt Times
Newspaper Date: 
4/27/1913
Page #: 
1
Column: 
4 & 5
Item Type: 
Jetty work
Place: 
South Spit Jacoby Creek Quarry
TEXT: 
20,000 tons of rock from the Jacoby Creek Quarry were delivered to the south spit & placed on the Jetty during the month of April. Hammond Construction Company is delivering 800 - 1000 tons/day. The new 108-ton crane which arrived on April 11th enables a vast amount of rock to be handled & placed. The crane can handle 20 tons out to 35 feet. Their contract requires them to deliver 1500 tons/day.
Key Words: 
Jetty, South Spit, Jacoby Creek Quarry