DT Data Page #:
470
Newspaper:
Humboldt Times
Newspaper Date:
4/27/1913
Page #:
1
Column:
4 & 5
Item Type:
Jetty work
Place:
South Spit Jacoby Creek Quarry
TEXT:
20,000 tons of rock from the Jacoby Creek Quarry were delivered to the south spit & placed on the Jetty during the month of April. Hammond Construction Company is delivering 800 - 1000 tons/day. The new 108-ton crane which arrived on April 11th enables a vast amount of rock to be handled & placed. The crane can handle 20 tons out to 35 feet. Their contract requires them to deliver 1500 tons/day.
Key Words:
Jetty, South Spit, Jacoby Creek Quarry
Microfilm Call # :